Quikrete Construction Materials is requesting a 15-year renewal of its Conditional Use Permit (CUP) to mine gravel and crush recycled asphalt (RAP) at Maryland Creek Ranch. Quikrete acquired Kilgore Companies LLC, and leases the land from owner, Everist Land Holdings, LLC.  Quikrete told the county the site lease continues through 2057. In anticipation of the Lower Blue River Planning Commission hearing, members of FOLBR sat down with the company's Community Engagement representatives for coffee.  

Board Member Jonathan Knopf and FOLBR member Harris Sherman met with Lindsay Newman and Eric Leigh to learn more about the company's short and long term plans. According to Leigh, the CUP application will be heard at the Lower Blue Planning Commission's August meeting. Interestingly, the Lower Blue Planning Commission's monthly meeting on August 2nd is listed as cancelled on the county website. So stay tuned, we'll let you know, when we know more.

According to Eric Leigh, the plant currently produces 400,000 tons of sand and gravel per year, all serving Summit County. Additionally, Quikrete produces about 100,000 tons of recycled asphalt (RAP) per year. Leigh indicated Cell 5 and 6 at Maryland Creek remain viable for mining aggregate. Cell 5 has an estimated four to five years left. Cell 6, where the processing facility sits, can be mined for roughly 20 more years. When mining begins on Cell 6, the processing facility will be relocated at the site.

Leigh continued saying once there is no more aggregate available to mine at Maryland Creek, the facility will become a manufacturing site, producing ready mix using imported rock and sand from other locations. The company will also continue to manufacture recycled asphalt. The mining operation, Leigh continued, will effectively cease. It is important to note, Quikrete's representatives did not indicate plans to mine the former Hilyard property, now home to Summit Valley Horse Center. The property is still owned by Kilgore Companies, which is owned by Quikrete.

We will let you know when the public hearing for the conditional use permit is confirmed. The hearing will be your opportunity to learn more and have your questions answered. Quikcrete plans an open house on Wednesday, July 22 at their Silverthorne Plant site.